Stornoway schedules diamond Production
Renard
3 to work from the 2019,
Production
is scheduled!
Since
earlier this year, Stornoway has been conducting a program of drilling and
sampling at the Renard with the goal of converting certain Mineral Resources to
Mineral Reserves, and of accelerating the mining of both the Renard 3 and
Renard 4 ore bodies in the Renard mine plan. Results to date are, 1: Renard 3
successfully delineated to a depth of 315 meters, supporting its inclusion in
the Renard production schedule above the 290 meter mining level in 2019,
several years earlier than currently planned.
2:
Renard 4 successfully sampled from surface, with approximately 3,000 carats
recovered to date, including three special stones, supporting its potential
development as a new open pit source of ore to supplement underground mine feed
to the Renard process plant.
Matt
Manson, President and CEO, commented: “The update provided today covers
activities that have been ongoing at Renard during the course of this year to
expand and accelerate ore supply options within the Renard Mine Plan. The
Renard 3 work is about accelerating the mining of high grade ore in our
production schedule, and maintaining over the long term a blend of ore from two
sources in the underground mine as we go deeper.
The
Renard 4 work is about expanding our understanding of the diamond population at
the top of the ore body prior to developing a potential new open pit. This
would require a water retention structure within Lagopède Lake, but would allow
us to take advantage of the expanded plant processing capacity offered by our
new ore-sorting circuit.
The
results of both of these resource development programs have been encouraging.
We expect to see the benefits of the Renard 3 work already in the 2019
production schedule, and we anticipate proceeding to the next stages of
economic study, community consultation and permitting following the completion of
the Renard 4 work, which remains ongoing at this time.”
Renard
3 was mined between 2016 and April 2018 in the Renard 2-Renard 3 open pit to a
depth of 120 meters. The current Renard mine plan contemplates the mining of
Renard 3 by underground methods between 2026 and 2027 following the completion
of mining at Renard 2.
During
the course of 2018, Renard 3 has been successfully delineated in 5,345 meters
of detailed drilling between 255 and 290 meters of depth, has confirmed the
expected location and width of Renard 3, and the continuation at depth of the
high grade Renard 3dg and 3h units that support the body’s high grade estimate
in the Mineral Resource statement. Renard 3 continues to be open at further
depth.
The new data are
being incorporated into a revised geological model and Mineral Resource
estimate for Renard 3, with a view to the incorporation of new Renard 3 Mineral
Reserves above the 290 meter level into the 2019 mining schedule.
Comments
Post a Comment