K92 plans 60K to 80K Ozs AuEq in 2019
By
describing positive results of the Preliminary Economic Assessment PEA K92
says, mining production and plant processing capacity could be increased to 400K
tonnes per annum over a period of approximately 12 months. Over a 13-year
period, the plant would treat 4.9 million tonnes averaging 9.0 g/t Au. 20 g/t
Ag.
Average
production would be of over 120K Oz AuEq per annum with cash costs of US$429/ Oz
AuEq and all-in sustaining costs. During the first five years, average
production would remain over 145K Oz AuEq per annum with Initial Capital Cost
of US$13.6 million for the expansion.
John
Lewins, K92, Canada, Chief Executive Officer, states, “The results of the PEA
show a robust project capable of producing almost 650K ozs Au over the next
five years and over 1.3 Mozs over a 13-year life. Importantly, development of a
new project, but for an expansion of our producing Kainantu operation which
produced over 45K ozs AuEq in 2018 at cash cost of below US$600/oz AuEq.
The
operation is expected to produce in excess of 60,000 ozs AuEq in 2019 assuming
no expansion, or over 80,000 ozs AuEq with the expansion envisaged in the PEA. K92
has established a strong operations team of mining professionals on the ground
in PNG which has seen the Kainantu Mine declare Commercial Production on Kora
North on February 1, 2018.